Pressure plate installation method and process


Pressure Plate Installation Method and Process

Roof Plate Hoisting Method

Cooling Bed Area H-K Span 39m, 200t Crawler Hanging Station Hoisted by Structure Outside the Span, Equipped with 30m Lifting Tools, Hoisting Pressure Plate to Roof, 200t Crawler Hoisting Main Rod 57m, Auxiliary Rod 19m, Working Radius 30m, Auxiliary Hook Lifting Weight 12t. The G-J span of the main rolling area is 66m across the 4-14 line. The 250t crawler hoisted by the structure is hoisted outside the span, equipped with 60m hoisting tools, and the pressure plate is hoisted to the roof. When the 250t crawler hoisted to the main pole 72m, the auxiliary pole 19m and the working radius 46m, the auxiliary hook lifting weight is 11.7t. The vertical lifting of the pressure plate shall be given priority by using special lifting equipment. If the vertical lifting cannot be met, the angle between the steel wire rope and the pressure plate shall be greater than 60 degrees.